Bláfjöll
- New chairlift Drottning in a modified position along with necessary measures and adaptation of slopes and terminals. Estimated lift launch is autumn 2023
- New chairlift Gosi in Suðurgil in a modified position along with necessary measures and adaptation of slopes and terminals. Estimated implementation time 2022.
- Used chairlift in Eldborgargil along with necessary modifications to terminals. Estimated implementation time 2026.
- New T-bar lift from Kerlingadalur. Estimated implementation time 2026.
Skálafell
- Used chairlift with necessary modifications to terminal facilities. Estimated timing 2023.
Snow Production
- snow production phase – Bláfjöll; home area, Kóngsgil and Öxlin. Estimated implementation time 2024
- snow production phase – Skálafell. Estimated implementation time 2025
The above project sequence and timing may change if technical or planning circumstances arise that require timeline revision.
Cross-Country Ski Trails
Continued development of the cross-country skiing area will be carried out with the installation of snow fences, poles, and signs, while the third phase of snow production will help ensure snow coverage on trails and extend the season for cross-country skiers.